Home Wiring Load Schedule: Wire and MCB for Every Circuit
A load schedule lists every circuit with its MCB and cable. In the example house the 6 circuits carry 9.98 kW; each gets the smallest copper cable that carries its current in 45 °C air within the voltage drop limit, the worst drop being 1.3%. The largest MCB is 20 A, for the Split AC 2 ton non-inverter.
What a home wiring load schedule is and why your electrician needs one
A load schedule, or circuit sheet, is the list an electrician wires the distribution board from: one line per circuit with what it feeds, its current, the MCB and the cable. In many Pakistani homes the whole house is wired on habit, the same 7/29 everywhere, which can leave the biggest AC circuit too thin and the lights oversized.
Fill in your circuits above, press Calculate and use Save as PDF to print the sheet. Each row uses the same rules as the wire size and MCB calculators on this site.
How the load schedule is worked out
Each row: current = design watts ÷ (230 V × power factor of the load type); an inverter AC is designed at its maximum input. MCB = next standard size at or above the current (× the margin for motors and compressors), curve by load type. Cable = smallest size whose rating in 45 °C air (B1, 1 per conduit, factor 0.79) covers the MCB and whose drop over the run stays within the limit (lighting or other). Connected load = 9,982 W over 6 circuits.
For each circuit: I = P ÷ (V × PF); MCB ≥ I; cable rating × derating ≥ max(I × margin, MCB); voltage drop = 2 × L × I × ρ ÷ A ≤ limit
- P = design watts of the circuit (watts × quantity; an inverter AC at its maximum input); V = supply voltage; PF = power factor of the load type
- MCB = next standard size; margin applies to motors and compressors; curve B, C or D by load type
- Derating = factor for the air temperature × factor for circuits grouped in one conduit
- L = cable length one way in metres; ρ = copper resistivity; A = cable area in mm²; limit lighting or other circuits
How each circuit's MCB and cable are chosen
The calculator turns each circuit's watts into amps at 230 V with the power factor of its load type. The MCB is the next standard size at or above that current, larger for motors and compressors that run near full current for hours. The curve follows the load: B for lights and heaters, C for sockets, ACs and motors.
The cable must carry more than the MCB lets through, after the rating is reduced for hot air and for circuits packed together, and the voltage drop over its length must stay within the limit. On short runs the current decides; on long runs, such as a water motor on the roof, the voltage drop often does.
MCB and cable for common home circuits (copper, in conduit, 45 °C air, one circuit per conduit)
| Circuit | Current | MCB | Cable | Voltage drop |
|---|---|---|---|---|
| LED tube light (4 ft) × 10, 20 m | 1.1 A | 6 A, curve B | 1 mm² (3/29) | 0.4% |
| Socket circuit (custom) × 1, 15 m | 10.9 A | 16 A, curve C | 2.5 mm² (7/29) | 1.3% |
| Split AC 1.5 ton inverter × 1, 12 m | 9.2 A | 16 A, curve C | 2.5 mm² (7/29) | 0.9% |
| Split AC 2 ton non-inverter × 1, 15 m | 13 A | 20 A, curve C | 4 mm² (7/36) | 1% |
| Electric geyser (storage, 40-gallon class) × 1, 10 m | 13 A | 16 A, curve B | 2.5 mm² (7/29) | 1% |
| Water pump / donkey motor 1 hp × 1, 25 m | 5.1 A | 10 A, curve C | 2.5 mm² (7/29) | 1% |
| Electric kettle × 1, 10 m | 8.7 A | 10 A, curve B | 2.5 mm² (7/29) | 0.7% |
Load schedules for real houses
Six-circuit house in conduit
6 circuits, 9.98 kW connected. The Split AC 2 ton non-inverter needs a 20 A C curve MCB on 4 mm² (7/36); the lights need only a 6 A MCB on 1 mm².
Same house with cables clipped on the surface
Surface cable cools better than cable in a wall conduit, so it carries more current: the Split AC 2 ton non-inverter circuit needs only 2.5 mm² on its 20 A MCB, one size less than in conduit.
Three circuits sharing one hot conduit
Grouping lowers every cable's rating (factor 0.55 with the air temperature), so the Electric geyser (storage, 40-gallon class) now needs 4 mm² (7/36).
Water motor on a long run to the roof tank
A Water pump 1.5 hp at 80 m draws only 8.2 A, but on the usual cable the voltage drop would pass the limit, so the sheet picks 4 mm² (7/36), a 3.2% drop, on a 16 A C curve MCB.
Connected load is not your sanctioned load
The sheet adds up 9.98 kW for the example house, but the lights, geyser, motor and both ACs rarely run together. The main switch and the sanctioned load are sized on the load that runs at the same time, which the sanctioned load calculator works out.
Keep each heavy appliance on its own circuit. Two ACs on one circuit need a bigger MCB and cable than either alone, and a fault on one switches off the other.
Load schedule rules in brief
- A home wiring load schedule (circuit sheet) gives each circuit its own MCB rating, MCB curve and cable size, so the electrician wires every room to the same rules.
- Every circuit is sized twice: the cable must carry the current at the hottest air temperature (45 °C by default), and the voltage drop over the run must stay within the limit for lighting or other circuits.
- Lights take a B curve MCB, sockets, ACs and motors a C curve; a Split AC 1.5 ton inverter gets a 16 A MCB on 2.5 mm² cable.
- The connected load of the example house is 9.98 kW, which is not the sanctioned load: not everything runs at once, so size the main switch and sanctioned load separately.
Printing the sheet and checking it on site
Use Save as PDF under the results to print the table or send it on WhatsApp. Ask the electrician to note the actual cable route length for each circuit, because a longer route than you guessed can push a circuit to the next cable size.
The sizes are planning values for copper PVC cable. Aluminium cable, three-phase supply and buried runs need a separate design by a licensed electrician.
When a UPS or inverter on one of these circuits trips or shows a fault, the inverter and battery troubleshooting tools help find the cause.
Wiring schedule mistakes
- Wiring the whole house in one cable size. Lights need far less, while an AC or geyser circuit needs more than the usual socket cable.
- Putting two ACs on one circuit. Each AC should have its own MCB and cable.
- Guessing the cable length as the straight distance. Measure the route through the walls and the ceiling, both ways are already counted.
- Adding up the connected load and calling it the sanctioned load. The main switch is sized on what runs at the same time.
Safety: This sheet is a planning aid for copper cable on a single-phase supply. A licensed electrician must confirm every cable, MCB, earth and RCD on site before the circuits are energised; cable ratings and the air temperature default await review by a PEC-registered engineer.
Home wiring questions
What is a load schedule in house wiring?
A list of every circuit on the distribution board with what it feeds, its current, MCB rating and curve, and cable size. The example house has 6 circuits and 9.98 kW connected.
Which wire and MCB for a 1.5 ton AC circuit?
For a Split AC 1.5 ton inverter on a 12 m run in conduit: a 16 A C curve MCB and 2.5 mm² (7/29) copper cable.
Which wire and MCB for an electric geyser?
The Electric geyser (storage, 40-gallon class) draws 13 A, so it takes a 16 A B curve MCB on 2.5 mm² cable.
Why does a long run need a thicker cable?
Voltage drop grows with length. On a long run the cable that carries the current safely can still lose too many volts, so the next size up is chosen; the sheet shows each circuit's drop.
Can I print this circuit sheet for my electrician?
Yes. Press Calculate, then Save as PDF under the results; the table prints with every circuit, or share the link on WhatsApp.
Is the total on this sheet my sanctioned load?
No. It is the connected load, everything at once. Use the sanctioned load calculator for the load that runs together.
Cable and breaker standards used
- IEC 60364-5-52: selection and erection of wiring systems (Table B.52.4 current ratings, voltage drop)
- Wattlyst methodology and default values
- Cable ampacity table (IEC 60364-5-52 Table B.52.4, PVC copper), last checked
- Appliance running and starting watts (Wattlyst appliance data, sources listed on the appliance list page), last checked
Last updated: